This is
the chronological events for the Project
|
17.Dec.2007 |
Corporate decision to
enter into Solar 100 MW plant |
|
11.Jan.2008 |
Company Euro Solar Power
Pvt. Ltd. Formed and Operational |
|
14.Jan.2008 |
Letter of intend submitted
to Gujarat Government |
|
12.Feb.2008 |
Letter of request
submitted to Gujarat Energy Development Authority |
|
03.Mar.2008 |
Land purchased for the
plant. Agreement Signed. Registration process started. |
|
20.Mar.2008 |
Weather station installed
and commissioned at site village Sivlakha, Taluka Bhachau, District Bhuj |
|
25.Apr.2008 |
Initial approval from
Gujarat Energy Development Authority (GEDA) received to set up 5 MW Grid
Interactive Solar PV based power plant under the Incentive based Generation
Scheme announced by Ministry of New & Renewable Energy, Government of
India (Click here to see the policy) (Click here to see the letter) |
|
23.May.2008 |
Initial Detailed Project
Report submitted to GEDA |
|
14.Jun.2008 |
Company team visited
Intersolar 2008 largest exhibition in Solar field in Germany to select and
evaluate the suppliers for the power plant |
|
29.Jun.2008 |
Petition submitted to
Gujarat Electricity Regulatory Commission (GERC) to fix up the feed in tariff
for the plant as this is the first plant in Gujarat. |
|
18.Jul.2008 |
Last three years
meteorological data obtained from Meteorological Centre, Bhuj |
|
28.Jul.2008 |
Detailed Land Survey
including contour mapping was done |
|
31.Jul.2008 |
Soil Chemical Report of
the land site is obtained. |
|
12.Aug.2008 |
Feed in Tariff order
received from Honourable Commissioner for feed in tariff. The commissioner
has granted the prevailing highest tariff set for other non conventional
source of energy. (Click here to see the
order) |
|
12.Aug.2008 |
Power Purchase Agreement
(PPA) signed with the Gujarat Urja Vidyut Nigam Ltd (GUVNL), a state
government owned electricity distribution company. The power purchase
agreement is signed for 30 years with a provision for tariff revision after
20 years. The applicable tariff is as per the tariff order received from GERC. |
|
25.Aug.2008 |
Application to other
state government agencies initiated. This includes pollution board clearance,
aviation clearance, water clearance, marine time clearance, electricity
evacuation clearance |
|
27.Dec.2008 |
Land Registration at
Sivlakha done, Certification obtained from local revenue authorities. |
|
29.Dec.2008 |
Project cleared from
Pollution Control Board of Gujarat State |
|
01.Jan.2009 |
Final state Clearance
application to GEDA |